Goodman Fielder Moorebank NSW
Tomlinson Energy Service recently carried out an upgrade of the boiler plant at Goodman Fielder Moorebank.
The task involved the removal of two Old Woodley Boilers built in the 60’s and replacing them with 3 x 500 kw Bosch Unit. It was a full Turnkey Installation which involved replacement of all components in Boiler house including Feedwater Tank and blowdown Tank.
The Bosch unit were CSB fitted with integral Economisers , Weishaupt burners with VSD and O2 Trim and Grundfos Pumps.
The overall nett boiler efficiency is approximately 88%. The entire project was carried out by Tomlinson Installation and Commissioning Team
Quality and Performance
Tomlinson Energy Service NSW, VIC and SA have a dedicated management system with a focus on Quality, Safety and Environmental aspects of all our operations.
Accredited to ISO 45001:2018, ISO 14001:2015 and ISO 9001:2015.